Việt Nam’s Residents Say No to State-Priced Land and Resettlement

A resident’s villa is demolished to make way for Gia Bình Airport. Photo: Quang Thăng / Facebook.

Last week, a reader asked why Luật Khoa Magazine consistently highlights the state taking people’s land at very low, state-set prices—one-half to one-third of the market price—while never mentioning that residents can also purchase resettlement land at similarly low state prices.

To illustrate this point, the reader noted that residents along the Red River (Sông Hồng) can buy resettlement land in Thư Lâm for 11 million đồng per square meter, compared to a market price of 80 million đồng per square meter. This example, however, requires clarification. According to VOV, the price the reader cited applies to households whose land was taken to build the Trần Hưng Đạo and Tứ Liên bridges, not the Red River Scenic Boulevard project. [1]

Prompted by this question, Luật Khoa Magazine surveyed and interviewed residents living within the planned zones of major projects in the capital, including the Red River project and the Vĩnh Hưng urban renovation, upgrading, and redevelopment project. Every interviewee strongly rejected the reader’s perspective, maintaining that residents lose out when the state takes their land.

Value Difference Between Seized Land and Resettlement Land

According to Luật Khoa Magazine’s survey, this discrepancy in land value is one of the primary reasons residents reject the reader’s argument. 

One Red River resident dismissed resettlement land as “land where dogs relieve themselves, rice fields, wasteland way out in the countryside”—a place where “dogs eat rocks and chickens eat ‘gravel’”—that cannot compare to the “golden land” being taken from them. Another argued that calculating the trade-off that way is “no different from saying 100/2 equals 40/2.”

Others echoed this frustration over location and livability:

“The problem is location! You get to buy cheap, but what good is that if the resettlement site is dozens of kilometers away? If they took our land cheap and then let us buy cheap 3 kilometers away, who would complain?”

“Can we be resettled in the Ciputra [an upscale development in Hà Nội] subdivision at state prices? Or will they push people 30 to 40 kilometers away, practically back to the countryside?”

“Resettle us somewhere with all the amenities first, then compare. These places are all far from everything, like going off to clear land and build a new frontier.

One resident summed up the exchange with a blunt analogy: 

“Say I came into your house, took your SH [a premium Honda scooter—Trans.], and gave you back an old Wave [a budget Honda motorbike—Trans.]. Would you be happy?”

These complaints have a solid basis. In Hồng Hà Ward, where land was seized to build the Trần Hưng Đạo and Tứ Liên bridges, Dân Việt newspaper reported that compensation ranged from 54 million to 128 million đồng per square meter, depending on location—rates that were already below market value. [2] 

Meanwhile, in Thư Lâm, where residents are being relocated, several state media outlets reported that brokers were advertising land for 70 million to 80 million đồng per square meter. [3] 

In other words, even the asking price for resettlement land merely matches or falls below the compensation residents received for their original properties, meaning the “profit” the reader described is calculated on a far lower baseline than the land residents lost.   

Moreover, the 80 million đồng per square meter figure in Thư Lâm does not necessarily reflect actual market transactions. Doanh nghiệp Hội nhập magazine has warned that brokers are inflating resettlement land prices in Thư Lâm, [4] reporting that even plots near high-voltage power line corridors and lots near cemeteries were advertised at more than 60 million đồng per square meter.

More importantly, any benefit from buying resettlement land at state prices only becomes real cash if residents sell their plots—forcing them to move yet again. If they choose to stay and live in Thư Lâm, that 80 million đồng per square meter valuation exists only on paper.

“Resettlement Areas are Built Like Pigsties”

A Red River resident complained to Luật Khoa Magazine that “the resettlement areas are built like pigsties; nobody stays there, and they are far away.” Many other interviewees voiced similar frustrations over the poor quality of resettlement infrastructure.

Speaking to Luật Khoa Magazine, a young man from the ancient village of Thúy Lĩnh in Lĩnh Nam Ward described the housing conditions bluntly:

“The resettlement apartments they build are not good. They are awful, really terrible. Just a little way in from here, they built a resettlement apartment building for people in Lĩnh Nam. Now people are saying the walls are already cracked, and they are selling a 60-square-meter unit for 2.5 billion đồng, but nobody is buying.” 

He added, “Around here [in Thúy Lĩnh—Ed.], 2.5 billion will not buy you anything anymore.”

His account matches reports in state media. In 2022, Kinh Doanh (VnBusiness), the online magazine of the Vietnam Cooperative Alliance, reported that two nine-story resettlement buildings in Lane 13 off Lĩnh Nam Street had sat abandoned for nearly 10 years after completion, with only a few units occupied and trash piled around their bases. [5] Notably, Lĩnh Nam has once again been selected as a resettlement site for the Red River project. [6]

The Thư Lâm resettlement area cited by the reader faces its infrastructure and delivery issues. In June 2026, VnExpress reported that a Hồng Hà resident living in temporary housing while waiting for resettlement land in Thư Lâm said that the site still lacked electricity, water, and clear fences or boundary markers. [7]

Although authorities promised to hand over the land within two weeks, three weeks passed with no word. Meanwhile, some resettlement areas for the Red River project are not expected to be completed until sometime between 2027 and 2030. [8]

Across Hà Nội, similar problems have persisted for years. [9] Buildings at major resettlement complexes—including Nam Trung Yên, the 7.2-hectare site in Ba Đình, Đền Lừ, and Lê Văn Lương—have deteriorated, fallen into disrepair, and been left abandoned. [10]

In Long Biên, three resettlement buildings in the Sài Đồng New Urban Area that were constructed more than 10 years ago remain abandoned and badly deteriorated after residents filed complaints and refused to accept the apartments.

Land Value and Livelihoods

For many residents, compensation is not simply a matter of trading land for land; it is also about protecting their livelihoods and leaving behind communities they have belonged to for generations.

A middle-aged woman in Vĩnh Hưng told Luật Khoa Magazine angrily, “What is the point of a lot of compensation if we lose our home and do not know where to go, where to move, or where to live?” 

She added that the land there “…is not like the Old Quarter, where they say it is worth 400 million per square meter. Here they compensate based on, say, the tax rate for category-4 land, which is 20 to 26 million per square meter. Doubled, that is only 52 million, still much lower than selling it ourselves. Selling it ourselves would now fetch at least 150 million per square meter, so at a minimum they should compensate people three times as much, 70 to 80 million, for it to be called fair. Even that would not be fair, because people have lived on this land for so many years, for generations. Now they pay a pittance and then take it to sell for profit, to make money for those investors.”

A resident of Lĩnh Nam also stated, “Take my family: our neighbors, and we have lived there for decades, for hundreds of years, since the time of our ancestors. Then one day, you open your eyes in the morning, and they say you have to move. That is what you call uprooting your whole environment.”

He added, “Say I had worked at some company for about 10 years and was told to switch companies. Even that would feel new to me, let alone moving house. It is just that we are forced, so we have to change.” 

“Can cheap prices make up for that? And where is the social security in all this?” another interviewee asked angrily.

As these accounts show, land recovery plans typically measure losses strictly in terms of land area, house value, and compensation and support payments. Yet a home is worth far more than the cost of building it—it is tied to livelihoods, social relationships, and living conditions established over many years.

After relocation, small vendors risk losing regular customers, workers face longer commutes, children may have to change schools, and older residents must leave behind neighbors, hospitals, and familiar surroundings. Such losses are difficult to quantify or offset with cash.

At Sun Group’s project in Vĩnh Hưng Ward, authorities and the developer have promised on-site resettlement, allowing households to rent or own commercial space in apartment buildings at preferential rates to maintain their businesses and stabilize their lives. [11]

Still, several questions remain unanswered: how much those “preferential” rates will be, who will qualify, and whether residents who currently run street-level shops along the lanes can retain their regular customers after moving into an apartment complex.

Under Article 108 of the 2024 Land Law, residents are eligible for support payments alongside compensation—covering living-condition stabilization; production and business stabilization; livestock relocation; vocational training, career transitions, and job seeking; and resettlement when compensation falls short of a minimum resettlement unit. [12] 

However, these payments are modest compared with housing and land prices. In Lào Cai Province, for instance, authorities calculate post-recovery living stabilization support as a cash payment of 30 kilograms of rice per person per month. [13]

Lawmakers have also raised concerns about social security during state land seizures. On Oct. 29, during the National Assembly debate on the draft amended Land Law—which was expected to be passed on Nov. 21—Deputy Nguyễn Bình Tân of Cà Mau argued that the legislation should establish a principle bringing compensation close to actual prices while accounting for residents’ ability to secure new housing and restore their livelihoods. [14] 

Tân also stressed that land recovery policy must ensure post-relocation stability and reflect the real losses borne by displaced residents. However, it remains unclear whether the state took into account the views of this deputy and thousands of affected residents.

Is the State Profiting at Both Ends?

Some residents even believe that the state profits twice: first by seizing land at low prices and again by selling resettlement land.

“State prices, but that land [resettlement land—Ed.] comes from rice fields. Its original price is only one-tenth. The people lose at both ends,” one person said. 

Another put it angrily: “They take our heads and our necks; they get us at both ends.”

One interviewee went further, demanding: 

“So why not take the problem back to the bastards who drew up a project to take our land? They should go over there and build their project. There is plenty of land over there. Even if they drew their ancestors’ graves on it, there would still be land to spare. Why do they have to steal our land and herd us over there?”

The claim that resettlement land originates as cheap farmland is accurate. The Thư Lâm resettlement area cited by the reader was itself carved out of local agricultural land.

On June 1, 2026, Thư Lâm Commune Chairman Phạm Trọng La stated that the Thư Lâm and Đông Anh multipurpose urban area project requires about 373.4 hectares of land, including about 274 hectares of agricultural land and 99.4 hectares of public and nonagricultural land managed by the commune. [15] 

According to La’s report, as of June 1, local authorities had paid nearly 1.254 trillion đồng in compensation to 792 households for 166.25 hectares—an average of less than 1 million đồng per square meter, far below the 11 million đồng per square meter the state charges resettled residents.

It should be noted that the 11 million đồng per square meter figure includes the cost of roads, electricity, water, and other technical infrastructure; hence, not all of the difference can be called the state’s “profit.” Regardless, both the farmers who lost land in Thư Lâm and the residents who lost homes in Hồng Hà had their properties valued at state prices, while neither group received the surge in land value created after planning.

Even experts who support urbanization acknowledge that this disparity must be addressed. Đặng Hùng Võ, a professor and former deputy minister of natural resources and environment, said that the state needs a mechanism to capture part of this added value and reinvest it in infrastructure for the public good. [16]

Upcoming legislation, however, may only strengthen the sense that the state is “profiting at both ends.” The draft amended Land Law has dropped provisions on “specific land prices and land valuation consulting organizations.” [17] Instead, compensation will be calculated by multiplying the provincial land price table by a compensation rate for each land category. 

With the provincial People’s Council deciding the land price table and the provincial People’s Committee setting the compensation rate, residents are left with almost no independent mechanism to verify these figures.

Resettlement Land is Limited

Many residents are also frustrated by the reader’s argument because not everyone qualifies for resettlement in the first place. 

“As if there were enough resettlement land. There are only a few thousand slots,” one person told Luật Khoa Magazine.

Planning data suggests this concern is well founded. In Vĩnh Hưng Ward, the draft 1:500-scale detailed plan allocates 14.4 hectares for resettlement and social housing—enough for the on-site resettlement of about 7,250 households—within a redevelopment area covering roughly 206 hectares. [18]

For the Red River project, the announced supply of resettlement land has shifted over time. In early 2026, media reports stated that the project would include four urban resettlement areas totaling about 113.5 hectares. [19] By September 2026, that figure had risen to about 265 hectares. [20] Although this land is intended to serve more than 247,000 affected people, how many will actually qualify for resettlement remains unanswered publicly.

From a legal standpoint, some people whose land is seized do not receive land compensation or a resettlement plot. Under Article 95 of the current Land Law, land users qualify for land compensation only if they belong to a legally specified group and possess legal documents or another lawful basis. [21] Without that basis, entitlements typically cover only property and investment costs. Resolution 254/2025, which took effect on Jan. 1, 2026, further devotes Clause 10 of Article 3 to listing cases ineligible for land compensation. [22]

In neighborhoods that developed informally over decades—such as along the Red River [23] or in Vĩnh Hưng Ward—many households lack formal paperwork, making it even harder for displaced residents to access resettlement benefits.


Taken together, these realities show that the reader’s “sell cheap, buy cheap” math is far from fair to displaced residents. Land recovery in Việt Nam has never been a straightforward exchange in which families receive full compensation and immediately step into an affordable resettlement plot to rebuild their lives.

State prices may apply in both directions, covering both land acquisition and resettlement. In practice, however, the taking is fast and certain, while the giving back is slow and inadequate in every respect.

In Gia Bình, Bắc Ninh Province, residents remain in urgent need of help. [24] Their land has been seized and their houses demolished, yet months later, the compensation and resettlement plots meant to offset their losses have still not arrived—leaving them with nothing to do but keep pleading and waiting.


Thực Sơ wrote this article in Vietnamese and published it in Luật Khoa Magazine on Nov. 18, 2026. The Vietnamese Magazine translated it into English. 

  1. Như Nguyên, “Đền bù, tái định cư khu vực ngoài đê sông Hồng (Hà Nội): Mấu chốt tạo đồng thuận” [Compensation and resettlement in the area outside the Sông Hồng dike (Hà Nội): The key to building consensus], VOV, May 14, 2026, https://vov.vn/xa-hoi/den-bu-tai-dinh-cu-khu-vuc-ngoai-de-song-hong-ha-noi-mau-chot-tao-dong-thuan-post1291655.vov.
  2. Phạm Hưng, “Giải phóng mặt bằng cầu Trần Hưng Đạo” [Site clearance for the Trần Hưng Đạo Bridge], Dân Việt, April 18, 2026, https://danviet.vn/giai-phong-mat-bang-sieu-du-an-cau-tran-hung-dao-nguoi-dan-than-toc-don-nha-d1419568.html.
  3. Trần Hoàng, “Đất tái định cư di dời dự án cầu Tứ Liên, Trần Hưng Đạo: Sang tay nhanh 80 triệu/m2” [Resettlement land for people relocated by the Tứ Liên and Trần Hưng Đạo bridge projects: Quickly changing hands at 80 million đồng per square meter], Tiền Phong, May 5, 2026, https://tienphong.vn/dat-tai-dinh-cu-di-doi-du-an-cau-tu-lien-tran-hung-dao-sang-tay-nhanh-80-trieum2-post1840624.tpo.
  4. T. Linh, “Hà Nội: Báo động tình trạng môi giới, thổi giá đất tái định cư tại xã Thư Lâm” [Hà Nội: Alarm over brokers inflating resettlement land prices in Thư Lâm Commune], Doanh nghiệp và Hội nhập, May 28, 2026, https://doanhnghiephoinhap.vn/ha-noi-bao-dong-tinh-trang-moi-gioi-thoi-gia-dat-tai-dinh-cu-tai-xa-thu-lam-137731.html.
  5. “Giải bài toán cung cầu nhà ở từ nguồn nhà tái định cư” [Solving the housing supply-and-demand problem with resettlement housing], VnBusiness, May 31, 2022, https://vnbusiness.vn/giai-bai-toan-cung-cau-nha-o-tu-nguon-nha-tai-dinh-cu.html.
  6. Văn Hưng, “Siêu dự án sông Hồng: Hé lộ 3 khu tái định cư cho người dân” [Sông Hồng megaproject: Three resettlement areas for residents revealed], Dân Trí, May 6, 2026, https://dantri.com.vn/bat-dong-san/sieu-du-an-song-hong-he-lo-3-khu-tai-dinh-cu-cho-nguoi-dan-20260506094301297.htm.
  7. “Cuộc sống tạm cư của những hộ dân nhường đất xây cầu” [Life in temporary housing for households that gave up their land for bridge construction], VnExpress, June 4, 2026, https://vnexpress.net/cuoc-song-tam-cu-cua-nhung-ho-dan-nhuong-dat-xay-cau-5080325.html.
  8. Diễm Hạnh and Elle Nguyễn, “Lộ trình dự kiến hoàn thiện nhà tái định cư, di dời dân ven sông Hồng” [Expected timeline for completing resettlement housing and relocating residents along the Sông Hồng], VnExpress, September 21, 2026, https://vnexpress.net/lo-trinh-du-kien-hoan-thien-nha-tai-dinh-cu-di-doi-dan-ven-song-hong-5122515.html.
  9. “Gỡ khó cho chung cư tái định cư” [Removing obstacles for resettlement apartment buildings], Báo Đầu tư, November 18, 2026, https://baodautu.vn/go-kho-cho-chung-cu-tai-dinh-cu-d72219.html.
  10. M. Tuấn, “Hàng nghìn căn hộ tái định cư bỏ hoang tại Hà Nội” [Thousands of resettlement apartments abandoned in Hà Nội], VietTimes, October 28, 2017, https://viettimes.vn/hang-nghin-can-ho-tai-dinh-cu-bo-hoang-tai-ha-noi-post62997.html.
  11. “Đô thị Vĩnh Hưng: Định hướng tái định cư tại chỗ cho 7.250 hộ dân” [Vĩnh Hưng urban area: On-site resettlement planned for 7,250 households], Báo Công Lý, October 14, 2026, via Báo Mới, https://baomoi.com/do-thi-vinh-hung-dinh-huong-tai-dinh-cu-tai-cho-cho-7-250-ho-dan-r56264827.epi.
  12. “Văn bản hợp nhất 44/VBHN-VPQH năm 2026 hợp nhất Luật Đất đai do Văn phòng Quốc hội ban hành” [Consolidated document 44/VBHN-VPQH of 2026 consolidating the Land Law, issued by the Office of the National Assembly], Thư Viện Pháp Luật, July 7, 2026, https://thuvienphapluat.vn/van-ban/Bat-dong-san/Van-ban-hop-nhat-44-VBHN-VPQH-2026-Luat-Dat-dai-699655.aspx.
  13. Sở Nông nghiệp và Môi trường tỉnh Lào Cai, “Bản so sánh, thuyết minh dự thảo văn bản quy phạm pháp luật sửa đổi, bổ sung với văn bản quy phạm pháp luật hiện hành” [Comparison and explanation of draft amendments to the current legal document] (draft amendments to Quyết định 18/2025/QĐ-UBND, Ủy ban Nhân dân tỉnh Lào Cai, 2025), https://storage-vnportal.vnpt.vn/lci-ubnd-responsive/8149/CSDL/B%E1%BA%A2N%20SO%20S%C3%81NH-%20THUY%E1%BA%BET%20MINH%20%28s%E1%BB%ADa%2019h%2024.12%29.pdf.
  14. “Đề xuất bổ sung nguyên tắc bồi thường tối thiểu khi thu hồi đất” [Proposal to add a minimum compensation principle for land recovery], VnExpress, October 29, 2026, https://vnexpress.net/de-xuat-bo-sung-nguyen-tac-boi-thuong-toi-thieu-khi-thu-hoi-dat-5138166.html.
  15. Bảo Bình and Nguyễn Thị Hoài Phương, “Hà Nội đẩy nhanh tiến độ hai dự án khu đô thị đa mục tiêu, tạo quỹ nhà tái định cư chất lượng cao” [Hà Nội speeds up two multipurpose urban area projects to create high-quality resettlement housing], Trang Thông tin Tuyên truyền, Phổ biến Pháp luật, June 1, 2026, https://pbgdpl.hanoi.gov.vn/chi-tiet-tim-kiem/-/asset_publisher/kyB8zPQFRdzV/content/ha-noi-ay-nhanh-tien-o-hai-du-an-khu-o-thi-a-muc-tieu-tao-quy-nha-tai-inh-cu-chat-luong-cao?_101_INSTANCE_kyB8zPQFRdzV_viewMode=view.
  16. Đình Sơn, “Dự án tái thiết Vĩnh Hưng: Tái định cư tại chỗ là chính sách tuyệt vời” [Vĩnh Hưng redevelopment project: On-site resettlement is an excellent policy], Thanh Niên, October 23, 2026, https://thanhnien.vn/du-an-tai-thiet-vinh-hung-tai-dinh-cu-tai-cho-la-chinh-sach-tuyet-voi-185261023104822313.htm.
  17. Thành Phương, “Sửa Luật đất đai: Bỏ giá đất thực tế, áp giá thu hồi theo bảng giá của tỉnh” [Amending the Land Law: Actual land prices dropped, provincial price tables applied to land recovery], Luật Khoa, October 23, 2026, https://luatkhoa.com/2026/10/sua-luat-dat-dai-bo-gia-dat-thuc-te-ap-gia-thu-hoi-theo-bang-gia-cua-tinh/.
  18. Kỳ Duyên, “Quy hoạch 1/500 đô thị Vĩnh Hưng: Công viên cây xanh tăng 22 lần, đất công cộng tăng gần 4 lần” [Vĩnh Hưng urban area 1:500 plan: Green parks grow 22-fold, public land nearly fourfold], Thị trường Tài chính Tiền tệ, October 16, 2026, https://thitruongtaichinhtiente.vn/quy-hoach-1-500-do-thi-vinh-hung-cong-vien-cay-xanh-tang-22-lan-dat-cong-cong-tang-gan-4-lan-86336.html.
  19. Văn Hưng, “Diễn biến mới tại siêu dự án sông Hồng sau khi Đèo Cả, MIK Group xin rút” [New developments at the Sông Hồng megaproject after Đèo Cả and MIK Group ask to withdraw], Dân Trí, January 10, 2026, https://dantri.com.vn/bat-dong-san/dien-bien-moi-tai-sieu-du-an-song-hong-sau-khi-deo-ca-mik-group-xin-rut-20260110094911105.htm.
  20. Văn Anh, “Hà Nội dự kiến bố trí 265ha đất tái định cư cho Dự án Trục đại lộ cảnh quan sông Hồng” [Hà Nội plans to allocate 265 hectares of resettlement land for the Sông Hồng Landscape Boulevard project], Đại Biểu Nhân Dân, September 6, 2026, https://daibieunhandan.vn/print/10429699.html.
  21. “Văn bản hợp nhất 44/VBHN-VPQH.”
  22. “Nghị quyết 254/2025/QH15 quy định cơ chế, chính sách tháo gỡ khó khăn, vướng mắc trong tổ chức thi hành Luật Đất đai do Quốc hội ban hành” [Resolution 254/2025/QH15 on mechanisms and policies to resolve difficulties and obstacles in implementing the Land Law, issued by the National Assembly], Thư Viện Pháp Luật, October 24, 2026, https://thuvienphapluat.vn/van-ban/Bat-dong-san/Nghi-quyet-254-2025-QH15-chinh-sach-thao-go-kho-khan-trong-to-chuc-thi-hanh-Luat-Dat-dai-684580.aspx.
  23. Thiện Mỹ, “Cấp ‘sổ đỏ’ ở vùng ven sông Hồng thuộc phường Phú Thịnh, thị xã Sơn Tây: Vướng ở đâu, gỡ dứt điểm ở đó” [Issuing “red book” land titles along the Sông Hồng in Phú Thịnh Ward, Sơn Tây Town: Resolving each snag where it arises], Hànộimới, September 29, 2023, https://hanoimoi.vn/cap-so-do-o-vung-ven-song-hong-thuoc-phuong-phu-thinh-thi-xa-son-tay-vuong-o-dau-go-dut-diem-o-do-643457.html.
  24. Lê Sáng, “Dự án Gia Bình: Dân rời biệt thự đi tạm cư, mấy tháng chưa được đền bù” [Gia Bình project: Residents leave villas for temporary housing, still uncompensated after months], Luật Khoa, November 5, 2026, https://luatkhoa.com/2026/11/du-an-gia-binh-dan-roi-biet-thu-di-tam-cu-may-thang-chua-duoc-den-bu/.